Ladle Capacity Expansion and Optimization Plan for Refractory Masonry and Bottom Blowing Processes After Expansion

The actual operating volume of a company’s ladle severely impacted the production rhythm of its converter and restricted the efficiency of its 300-ton converter. The average output of 300-ton converters, both domestically and internationally, should exceed the nominal design capacity. However, the company’s average output was less than 290 tons, a significant bottleneck that had long hindered production efficiency. Therefore, the company resolved to increase the capacity of its ladle, completely resolving the various drawbacks caused by the undersized ladle and achieving efficient and stable production.

01 Ladle Capacity Expansion and Renovation

1.1 Ladle Capacity Expansion and Renovation Requirements

To reduce renovation costs, the company decided to maximize the use of the existing cladding, reusing the ladle bottom, bottom supports, and tilting mechanism. The ladle bottom maintained its existing dimensions, with the large supports around the trunnion seat and the ladle base reused. The weld seam with the shell and the heat-affected zone were removed, with a 35mm cut on each side. The length of the trunnion embedded in the trunnion seat was shortened accordingly, keeping the inner trunnion fixing block and protrusion aligned with the original ladle inner wall. The ladle tilting mechanism was reused with the same dimensions. The ladle bottom was first removed along the weld seam, with a height of 90mm removed. The weld between the ladle wall and the ladle bottom was changed from being flush with the inside of the ladle bottom to being flush with the outside. The transition weld was completed, and the corners were polished to a smooth R20mm. The ladle bottom, which had a small step before the renovation, is now flush with the ladle wall. The thickness of the permanent ladle layer will be maintained after the construction. The ladle body diameter increased by approximately 68mm after the capacity expansion, necessitating the replacement of the ladle body steel plate. To ensure strength, the plate thickness was increased from 40mm to 42mm. The ladle trunnion and trunnion seat are the most critical parts of ladle handling.

Currently, the 37 existing ladles are over 8 years old. The trunnions have worn during handling. For safety reasons, the trunnions were replaced during the capacity expansion and renovation. To ensure the ladle’s external dimensions remained unchanged after the capacity expansion, the hoop and base were redesigned after approval by the design institute. The internal dimensions were shortened, but the plate thickness was increased to ensure strength. The horizontal distance between the ladle cover hinge and the ladle top was reduced by 35mm. The ladle cover diameter is the same as the ladle’s external diameter, and the hinge seat was fabricated and constructed according to the drawings.

1.2 Impact on Other Equipment

The increased ladle shell size after the ladle capacity expansion had a certain impact on related equipment. During the ladle capacity expansion and renovation, key constraints were fully considered, including the 480t overhead crane gantry hook, offline ladle baking, molten steel car, 480t cross-car, LF furnace, RH furnace, CAS furnace, ladle cover system, and caster turret. These core equipment remained unchanged, while other auxiliary equipment was appropriately adjusted to ensure smooth operation of the project. ① Impact of the Capacity Expansion on the Gantry Hooks

Currently, the center-to-center distance of the 480t overhead crane gantry hooks is 5600mm. With the increased cladding diameter, ensuring the proper and safe handling of the ladle without replacing the gantry hooks became a crucial issue. To ensure gantry hook stability, after rigorous verification, the ribs on both sides of the ladle were shortened in the width direction and thickened, ensuring the same spacing between the gantry hooks. With the increased ladle capacity, each ladle of molten steel has increased from 290t to 320t. The cladding weighs approximately 71t, the refractory material approximately 80t, and the total weight is approximately 470t. The overhead crane supports a load of 480t, so the increased capacity does not exceed the overhead crane load.

② Impact of the Capacity Expansion on the Ladle Tying

The ladle diameter increased by approximately 68mm after the capacity expansion. Therefore, the original cladding used for tying the permanent layer needed to be discarded. The cladding diameter was increased accordingly to accommodate the newly increased capacity. The dimensions and structure of other components remained unchanged. ③ Impact of the expansion on ladle-related ancillary equipment

The increased ladle height does not increase, thus having no impact on offline ladle baking, LF furnaces, RH furnaces, and CAS furnaces. However, the increased ladle thickness does affect the ladle cover, ladle cradle, ladle car seat, and ladle turret fork. To minimize changes to existing equipment dimensions, the equipment specialists, through on-site surveying and testing, ultimately reached a consensus: the new ladle mouth diameter will be 4700mm, equivalent to the ladle cover diameter. To prevent the ladle cover from falling into the ladle, the permanent layer and refractory brickwork must be completed before the ladle cover is installed. The increased ladle seat diameter will be 4386mm. The clearance between the ladle car and ladle fork after insertion will decrease from 35mm to approximately 10mm. This reduction in clearance will affect the smooth insertion of the ladle into the ladle turret. Therefore, the wear-resistant strips on the ladle car seat and ladle fork will be ground and thinned by 15mm. Furthermore, the manufacturer will be required to maintain a negative tolerance when manufacturing the ladle diameter.

1.3 Ladle Masonry Requirements for Capacity Expansion

Before the permanent layer of the ladle wall is knotted, asbestos board is laid on the ladle wall, using lightweight castables for knotting. The water content of the lightweight castable should be controlled at approximately 6% to 8%, and the mixture should be mixed evenly. The new ladle mold should be set and the process should be carried out according to existing process requirements. The ladle bottom should be knotted with heavy castables. The ladle bottom and nozzle support bricks should continue to be laid using the existing masonry method: first install the upper and lower support bricks, then lay the bottom bricks. The gaps between bricks should be less than 2mm, and the brick joints should be staggered vertically and horizontally, with mortar filling the joints. The ladle bottom masonry should be aligned and securely locked. For ladle shells undergoing capacity expansion and renovation, 190mm lining bricks should be used for the working layer of the ladle wall, and 210mm magnesia carbon bricks should be used at the slag line. They must have been used for at least 25 times before the ladle can be officially restored to full capacity. For ladle shells undergoing intermediate repairs, 180mm lining bricks should be used for the working layer of the ladle wall, and 210mm magnesia carbon bricks should be used at the slag line.

02 Ladle Bottom Blowing Optimization

2.1 Optimizing the Air Brick Structure

During the use and pouring process of existing slit-type air bricks, high-temperature molten steel and slag could penetrate through the gaps in the bottom-blowing air bricks, causing blockage of the air passages by the seeping steel and slag. Therefore, a new type of slit-type composite diffused air brick was designed and manufactured, as shown in Figure 1.

This permeable brick primarily consists of an argon rigid tube, a core brick, a truncated cone (slit block), a dispersion block, and a core base brick. The argon rigid tube is welded to the iron sheet of the core brick. The truncated cone (slit block) is installed in the lower interior of the core brick. The dispersion block is installed above the cone (slit block) within the core brick. The core base brick is the outermost brick, enclosing the upper portion of the argon rigid tube and the core brick. Figure 1: Slit-dispersion composite permeable brick. After trial and promotion, it was found that this composite bottom-blowing brick can meet current normal usage. The permeability has increased from 99.72% to a stable level above 99.85%, ensuring the bottom blowing efficiency of the ladle.

2.2 Improving the permeable brick material to increase its lifespan

The original bottom-blowing permeable brick was primarily composed of tabular corundum, spinel, and chromium oxide. In actual use, it was found that its thermal shock resistance and compressive strength were low. It could deteriorate under the hot pressure of molten steel, affecting its lifespan and blowing efficiency. Therefore, the introduction of aluminum-magnesium spinel and chromium corundum was considered to enable the formation of microcracks in the air bricks under alternating hot and cold environments, buffering the thermal stress caused by temperature fluctuations, reducing spalling, and improving thermal shock resistance. Furthermore, considering the large 300t ladle with an effective height of 4m for molten steel, the compressive strength of the bottom-blown air bricks must be enhanced. Therefore, the alumina powder content was appropriately adjusted. The improved air brick material is primarily composed of approximately 80% corundum, aluminum powder, approximately 2.5% chromium oxide, and magnesium-aluminum spinel, with approximately 3% binder added.

For dephosphorization furnace steelmaking, if the ladle bottom-blowing bricks have a service life of more than 15 batches, to ensure the success rate of bottom blowing, 10kg of drainage sand is placed in each of the east and west bottom-blowing brick grooves after the bottom blowing is completed and the drainage sand is added. The remaining thickness of the air bricks after unpacking is monitored regularly to maximize their utilization and extend their service life, ensuring safe use. If the bottom-blowing bricks have a lifespan of 20 or more heats, or if severe corrosion is observed, the depth of corrosion should be measured using specialized tools tailored to the size of the tilting machine. If the depth of corrosion exceeds 280 mm, the ladle must be discarded. These measures have increased the average service life of the ladle bottom-blowing bricks from 23 heats to 25 heats, significantly improving the average interval between ladle repairs.

2.3 Optimizing the Purge Device

After the ladle cover project was fully operational, the ladle lining temperature reached temperatures exceeding 1300°C. Conventional oxygen-burning pipes would bend upon entering the ladle, significantly increasing the difficulty of purging. Failure to effectively purge the ladle bottom-blowing bricks resulted in insufficient air permeability, significantly increasing the number of abnormal bottom-blowing heats in refining. To address this issue, improvements were made to the purge device. This device uses an inner and outer tube connected by a retaining ring. The gas pipe is welded to the outer tube and connected to it. The handle is welded to the outer wall of the outer tube. The space between the outer and inner tubes provides a gas passage, ensuring rapid purging of the covered ladle bottom-blowing bricks while preventing over-purging of the bricks during oxygen-burning purging, which could reduce their service life.

2.4 Optimizing the Bottom Blowing Process

To prevent leakage from the automatic bottom-blowing piping, the automatic bottom-blowing piping for the ladle has been changed from exiting the ladle’s mushroom-shaped female end and then descending into the ladle bottom to connect to the manual cannula. Instead, it exits the mushroom head and then ascends along the ladle wall, passing through the ladle reinforcement holes and connecting to the manual cannula on the left side. When the automatic bottom-blowing piping is not in use or when leakage occurs at the mushroom-shaped end of the automatic bottom-blowing piping, the valve of the automatic bottom-blowing piping is closed and the manual cannula is used for bottom blowing. To check for leaks in the backflush piping of ladle bottom-blowing bricks: First, close the argon pressure reducing valve, open the main argon valve, and observe the flow rate display. If the display shows less than 50 L/min, there are no leaks in the piping. If the display shows more than 50 L/min, there may be leaks in the backflush piping and joints, which require inspection and prompt rectification. After implementing the above four measures to optimize the bottom-blowing process, the ladle’s success rate has significantly improved. The annual average success rate has increased from 99.84% and stabilized at over 99.98%. The average service life of the ladle bottom-blowing bricks has increased from 23 to 25 furnaces, and the number of ladle units offline due to bottom-blowing bricks has decreased by five per month.

03 Application Results

Since the company’s expanded ladle capacity came online, the molten steel loading capacity has increased from 290 tons to the current 310 tons, laying a solid foundation for stable and high-quality production in the steelmaking department. The annual capacity of the first steelmaking converter has increased by 7%, approximately 630,000 tons, bringing the total annual capacity to 9.7 million tons, approaching the output level of Pohang Gwangyang. The ladle capacity expansion and renovation has effectively boosted steelmaking output, minimizing the impact of single-furnace auxiliary operations on production. Furthermore, the increased output per furnace has reduced power, refractory, and labor costs per ton of steel, significantly reducing production costs. Furthermore, the introduction of slit composite diffused air bricks at the ladle bottom, a new coal-oxygen lance, and improvements to the bottom-blowing process have increased the blow rate from 99.84% to a stable level above 99.98%. The lifespan of the bottom-blown bricks has also been significantly improved, reaching the standards of leading steel plants.

LMM YOTAI established in 2007. Our production technology comes from Japanese Yotai. As an experienced and international player in the refractories industry. We have succeeded in expanding both the breadth of its product range and the depth of its services. From raw material selection, refractory portofio & optimization, installation & services & recycle of used refractories on site to further reduce client’s Opex & Capex in refractory consumption per ton steel output, meanwhile improve product quality of client.

Our Product have been supplied to world’s top steel manufacturer Arcelormittal, TATA Steel, EZZ steel etc. We do OEM for Concast and Danieli for a long time

Facebook
LinkedIn
Pinterest
Reddit

Comprehensive solution of Refractory for steelmaking

Fill out the form below, and we will be in touch shortly.
Contact Information