Methods to extend the service life of the refining electric furnace lining

The refining electric furnace lining is currently made of magnesium ramming material, which is often used to produce medium and low carbon ferromanganese or medium and low carbon ferrochrome. The service life (furnace age) of the medium and low carbon ferromanganese lining is generally about 400 furnaces. If it encounters peak production, its service life is shorter. The lining life plays a very important role in production. Too short service life will lead to a significant increase in product costs, while also reducing the production rate of the electric furnace and increasing the labor intensity of workers; even worse, it will also bring major hidden dangers to the safety of workers. Therefore, extending the service life of the electric furnace lining can not only reduce production costs, but also increase output to achieve the purpose of improving labor productivity. At the same time, it can reduce some safety hazards of workers and create greater economic benefits for the enterprise. This article discusses how to extend the service life of the refining electric furnace lining.

First of all, it is necessary to understand the use of medium and low carbon ferromanganese linings. At present, most of the magnesium ramming materials used in the industry are produced in Liaoning, Henan and other places. Its main components are shown in Table 1.

IngredientsMgOSiO2Fe2O3CaO
Content/%82486

Secondly, in the process of knotting, the furnace bottom is usually cleaned, and then the ramming material is added into the furnace, and the lining is knotted layer by layer with a vibrating rod. When the lining is knotted, it is put into production. The raw materials used in the production of medium and low carbon ferromanganese are generally manganese ore, manganese silicon processing powder or washed sand, lime. The method of arcing at the bottom of the manganese silicon processing powder is adopted. When the arc is stable, the mixed material is added and smelting begins. After meeting the requirements, it is discharged from the furnace.

The production process is basically in line with the production requirements of the cold charging process. The normal service life of its lining is about 400 furnaces. The actual production situation of most enterprises is similar. This article discusses the knotting material, knotting process, raw materials, production process and peak avoidance production.

Requirements for knotting materials

It can be seen from Table 1 that the MgO content in the knotting material is 82% and the SiO2 content is 4%. Since MgO is an alkaline oxide and SiO2 is an acidic oxide, the two can easily combine to form silicates at high temperatures. In the process of forming silicates, part of MgO can be consumed, which aggravates the damage of the lining. If the MgO content in the knotting material is increased and the SiO2 content is reduced, the probability of forming silicates will be reduced, which can ensure the life of the furnace lining at the source, so it is necessary to select special magnesium ramming materials to ensure the extension of the service life of the furnace lining. The composition of special magnesium ramming materials is shown in Table 2.

IngredientsMgOSiO2Fe2O3CaO
Content/%>83<1.54~68~10

01 Requirements during the knotting process of the electric furnace lining

During the knotting process, the lining is generally knotted layer by layer with dry ramming materials. In order to compact the knotting materials, the height of each layer is required to be no more than 200mm. A piece of colored strip cloth is placed on it, and then the colored strip cloth is divided into multiple circles of different sizes from outside to inside along the circular shape of the furnace bottom according to the diameter of the vibrating rod. After knotting, the vibrating rod is knotted back and forth along the arc in a clockwise and counterclockwise direction. Many companies use one-way knotting or irregular knotting methods. In fact, this method does not have a good knotting effect on the ramming materials. The clockwise and counterclockwise knotting method can be used to knot the holes of the knotted materials to the smallest, and the knotted material layers are the most reliable; after one layer is knotted, take out the colored strip cloth, and use a rake to rake out a “cross” groove about 20mm deep and 10mm wide on the knotted furnace bottom layer to facilitate the close combination between layers. In this way, the furnace bottom is not easily eroded during the production process, and its service life will naturally be extended.

02 Requirements for raw materials used in medium and low carbon ferromanganese

The raw materials used in medium and low carbon ferromanganese mainly include manganese ore, manganese silicon processing powder and lime. Among these raw materials, manganese ore has the greatest impact on the life of the furnace lining. Generally, wet manganese ore will cause scorching and stab fire after entering the furnace, which will cause great damage to the furnace lining. Therefore, it is necessary to keep the raw materials entering the furnace dry, which can extend the life of the furnace lining. Raw materials generally contain moisture to varying degrees. Especially in the south, due to heavy rain, manganese ore will be wetted by rain during transportation or storage. In order to ensure the dryness of the raw materials entering the furnace, a rotary kiln can be used for drying before entering the furnace for smelting. This can not only reduce production costs, but also reduce the erosion of the raw materials on the furnace lining.

03 Process requirements in the production process

(1) Requirements for pile bottom materials

Using manganese silicon processing powder to pile bottom arc can reduce the damage of the electrode arc to the furnace bottom. Under normal circumstances, 40% of the manganese silicon consumption can be extracted from the pile bottom, which can prevent the rapid consumption of the furnace bottom. However, when the furnace bottom is consumed slowly and the furnace wall is consumed too quickly, the life of the furnace lining will also be reduced. At this time, the bottom material should be removed immediately and all the mixed materials should be put into the furnace to ensure that the furnace bottom and the furnace wall are consumed synchronously and reasonably.

(2) Smelting time requirements for the first three furnaces

In order to ensure that the furnace bottom sintering meets the requirements and the furnace bottom does not turn over in the subsequent production process, the smelting time of the first furnace should be extended by 2 hours compared with the normal furnace time, and the second furnace can be extended appropriately. From the third furnace, normal production can be resumed.

(3) Timely furnace repair

During the consumption of the furnace bottom, there will be a phenomenon of rapid damage to the furnace wall. If the furnace is not repaired in time, the entire furnace lining will be destroyed. Therefore, when it is found that the furnace wall is severely damaged locally, stop and clean the slag hanging on the furnace lining around the damaged area, then fill the configured furnace repair material into it and tamp it, and then unload the material and power it on for production. Especially on both sides of the tapping hole, the molten iron will seriously scour here when tapping, so it is necessary to repair the furnace frequently.

(4) Timely adjustment of the pole center circle

The requirements for the pole center circle in the early and late stages of the furnace lining are different. In the early stage, the furnace bottom is thicker, the electrode position is higher, and the distance from the three-phase electrode to the furnace wall is larger. In the middle and late stages of the furnace lining, the electrode position is deeper, and the distance from the three-phase electrode to the furnace wall becomes smaller. At the same time, the furnace wall on the electrode side becomes thinner. If the pole center circle is not adjusted in time, the furnace wall will be damaged faster. Generally, in the middle and late stages of the furnace lining, the pole center circle should be adjusted smaller to ensure the extension of the life of the furnace lining.

04 Requirements for secondary voltage during production

When producing medium and low carbon ferromanganese, there are relatively strict requirements for secondary voltage. The 3MVA electric furnace uses a 5-level voltage, i.e. 153.7V, and the voltage does not need to be adjusted during production. If the voltage is too high, the arc will be too long in the late stage of production, which will damage the furnace lining. If the voltage is too low, the smelting time will be too long, which will also damage the furnace lining. Therefore, it is necessary to insist on using a suitable secondary voltage in production to help extend the life of the furnace lining.

05 Impact of peak-avoidance production on furnace lining

There are many situations of peak-avoidance production. Some only avoid the peak period for about 4 hours; some avoid the peak period for 8 hours; some only produce 10 hours during the off-peak period, which requires avoiding 14 hours; some avoid the peak continuously, some interrupt for a few hours in the middle, etc. No matter how the peak is avoided, the damage to the furnace lining is relatively large. In order to reduce the damage to the furnace lining caused by peak avoidance, measures need to be taken to protect the furnace lining. The specific measures are as follows:

(1) The last furnace of molten iron must be discharged cleanly to prevent the molten iron from corroding the furnace bottom during the shutdown period;

(2) After the last furnace of iron is discharged, the materials must be prepared according to the process requirements, and the furnace must be filled with materials to insulate the furnace lining to prevent the furnace lining from being weathered.

Conclusion

Through the analysis of the production characteristics of the refining electric furnace, the methods for extending the service life of the furnace lining are explained from the aspects of furnace lining materials, product raw materials, production process, electricity consumption system and peak avoidance production. As long as the above methods are strictly followed, the service life of the furnace lining of the 3MVA electric furnace producing medium and low carbon ferromanganese can be extended from about 400 furnaces to 800 furnaces.

LMM YOTAI established in 2007. Our production technology comes from Japanese Yotai. As an experienced and international player in the refractories industry. We have succeeded in expanding both the breadth of its product range and the depth of its services. From raw material selection, refractory portofio & optimization, installation & services & recycle of used refractories on site to further reduce client’s Opex & Capex in refractory consumption per ton steel output, meanwhile improve product quality of client.

Our Product have been supplied to world’s top steel manufacturer Arcelormittal, TATA Steel, EZZ steel etc. We do OEM for Concast and Danieli for a long time

Facebook
LinkedIn
Pinterest
Reddit

Comprehensive solution of Refractory for steelmaking

Fill out the form below, and we will be in touch shortly.
Contact Information