After the construction of the Refractory castables is completed, the mold maintenance is ≥24h, and the natural maintenance after demolding is ≥24h. In addition to taking warming measures in winter construction, the maintenance time should be longer. For time-sensitive repairs or emergency repairs, exhaust holes can be reserved on the mold, with a spacing of 100mm as the best, and disposable chopsticks are inserted into the exhaust holes to ensure gas discharge.
01
During winter construction, when the temperature is below -5℃, reliable cold prevention measures (windproof around the construction, fire, hot water mixing castables, etc.) must be taken before construction.
02
Warming measures must be adopted during winter construction, and the working environment must be sealed, windproof, heated and warmed to keep the temperature of the lining above 5℃ after masonry.
03
When constructing castables in winter, mix the materials with hot water, and keep the temperature of the mixed materials above 10℃. It is not advisable to add chemical accelerators or antifreeze agents.
04
When constructing in the furnace in winter, the insulation layer should be built first to improve the antifreeze ability of the refractory layer. After construction, the masonry should be covered with plastic cloth, and it is strictly forbidden to expose the masonry to the cold atmosphere.
05
In winter construction, adding salt or other substances as antifreeze agents can easily reduce the high-temperature performance of the material, or reasonable antifreeze measures are not taken during construction; the curing time is short, the baking is too fast, and the Refractory castables is easy to burst.
06
During construction on rainy days, measures such as covering, padding or covering should be taken, and it is strictly forbidden to soak the masonry in water.
07
When constructing on summer days with an ambient temperature of ≥30℃, the water temperature and material temperature should be controlled below 30℃, and it is strictly forbidden to expose it to the sun. After pouring, it should be covered with plastic film or straw mats in time, and water should be sprinkled frequently to cool down to avoid cracking due to excessive water loss.