Introduction
In the continuous casting process, preventing contact between molten steel and the atmosphere is essential for maintaining stable steel cleanliness and bloom quality. For this reason, a long shroud is commonly installed between the ladle and the tundish to provide a protected transfer channel for molten steel. Despite continuous improvements in long shroud casting technology — including optimized shroud design, automatic shroud installation systems, ceramic gasket sealing, and improved tundish flow control — complete prevention of atmospheric exposure during startup casting remains difficult.
During the initial stages of teeming, before the outlet of the long shroud becomes submerged beneath the molten steel bath, the molten steel stream flows through the tundish atmosphere as a free liquid jet. This transient condition may persist for several minutes until the steel level rises sufficiently to immerse the shroud outlet and establish stable casting conditions. During this period, the molten steel absorbs nitrogen and oxygen from the surrounding atmosphere, resulting in increased total nitrogen and oxygen contents in the steel.
This phenomenon of tundish nitrogen pickup and secondary oxidation eventually becomes evident in the solidified bloom or slab, leading to chemical composition fluctuations that may exceed specification limits. Consequently, steel producers frequently evaluate total nitrogen and oxygen contents in billets and slabs to assess the severity of molten steel atmospheric exposure during startup casting.
The problems associated with nitrogen and oxygen absorption during molten steel transfer and casting have been extensively investigated under both industrial and laboratory conditions. However, most previous studies related to the continuous casting tundish process mainly focused on nitrogen and oxygen pickup in the first slab or billet after startup. Comparatively fewer investigations have examined transient secondary oxidation and nitrogen absorption caused by direct exposure of molten steel to the tundish atmosphere during the initial filling stage.
Furthermore, limited attention has been given to the variation of nitrogen pickup along the strand length. In industrial practice, nitrogen fluctuations gradually decrease from the first bloom toward stable casting conditions, yet the relationship between tundish exposure time and the affected strand length remains insufficiently quantified.
Therefore, the objective of this study was to investigate nitrogen absorption caused by atmospheric exposure of molten steel during the startup stage of continuous casting through the long shroud and tundish system. Based on the results, a physics-based modelling method was developed to predict the strand length affected by elevated nitrogen content during continuous casting operations.
To support the modelling results, industrial measurements obtained from steel plant operations were also incorporated into the study.
Mechanism of Nitrogen Pickup During Initial Tundish Filling
During the first heat of continuous casting, nitrogen and oxygen present in the tundish atmosphere are transferred into the molten steel before the long shroud outlet becomes submerged. Nitrogen absorption only ceases once the outlet end of the long shroud is fully immersed beneath the molten steel bath.
This means that, during the initial tundish filling period, the incoming molten steel possesses a significantly different chemical composition compared with the steel present after stable casting conditions are established. As the molten steel level rises inside the tundish, the composition gradually changes until steady-state conditions are achieved.
Figure 1 schematically divides the initial casting stage of the first heat into two separate periods according to the immersion condition of the long shroud outlet.

Stage I
The period during which the outlet end of the long shroud remains above the molten steel surface and the steel stream is directly exposed to the tundish atmosphere.
Stage II
The period after the long shroud outlet becomes submerged and the nitrogen content gradually stabilizes toward steady-state casting conditions.
During Stage II, the weight and chemical composition of molten steel in the tundish progressively approach equilibrium. This transient mixing phenomenon is essentially similar to the grade intermixing behavior observed during sequential casting of different steel grades.
Because the composition variation in the tundish directly affects bloom chemistry and steel cleanliness, studying the mixing and nitrogen transfer behavior during startup casting is critical for improving product quality and reducing compositional fluctuations.
Full-Scale Water Model Simulation
To determine the volume of molten steel affected by atmospheric exposure and estimate the corresponding strand length influenced by elevated nitrogen content, mixing experiments were conducted using a full-scale physical water model of a two-strand tundish system.
In a typical experiment, the model tundish was initially filled with brine having a uniform conductivity. The brine level was maintained up to the outlet end of the long shroud. Fresh water was subsequently introduced into the tundish through the long shroud at a prescribed flow rate to simulate molten steel transfer during startup casting.
The two tundish outlets were opened simultaneously to simulate continuous casting operation. Conductivity probes manufactured by EUTECH™ were positioned near both tundish outlets to continuously monitor conductivity variations with time. The resulting conductivity-time response curves represented the transient mixing behavior occurring inside the tundish during the replacement of brine by fresh water.
The sequence of operations used in the simulation experiment is illustrated conceptually in Figure 2.

Stage 1 — Initial Filling
Brine entered the tundish until the outlet end of the long shroud became submerged.
Stage 2 — Mixing Stage
Fresh water gradually entered the tundish through the long shroud while conductivity measurements were continuously recorded at both tundish outlets.
Stage 3 — Stabilization Stage
Conductivity monitoring continued until the brine was completely replaced and stable flow conditions were achieved.
The physical dimensions and operating parameters used in the experiments were consistent with industrial casting practice.
|
parameter |
steel mill tundish |
Model |
|
Bottom length of tundish, mm |
1700 |
1700 |
|
The maximum width of the bottom of the tundish, mm |
600 |
600 |
|
The number of egress flows in the tundish |
2 |
2 |
|
Tundish nozzle diameter, mm |
40 |
40 |
|
Inner diameter of long nozzle, mm |
67 |
70 |
|
Tundish liquid depth under stable operating conditions, mm |
670-700 |
700 |
|
Distance between the outlet end of the shroud and the bottom of the tundish, mm |
500-550 |
535 |
|
Liquid volume of tundish, submerged from the liquid level to the fracture of the long nozzle, kg |
~4500 |
612.5 |
|
Casting rate, kg/min |
600-700 |
100 |
|
Estimated range of fluid exposure time in the tundish, s |
385-450 |
367.5 |
|
Mold cavity size: mm × mm |
200*200 | |
|
Casting speed: m/s |
0.015-0.0158 | |
|
Slab length, m |
4.1 |
(Annotation: The slab length 4.1m in the table is estimated to be a typo, because the slabs mentioned later are all 4.5m.)
Conductivity Measurement and Mixing Analysis
Several experiments were carried out under identical operating conditions to verify the reproducibility of the conductivity measurements. The results demonstrated excellent consistency between repeated experiments. Moreover, the conductivity variations measured at the two symmetrically positioned tundish outlets were almost identical, confirming the reliability of the physical model.
All experiments were performed under constant inlet and outlet flow conditions. Different casting conditions were simulated either by adjusting the stopper rod opening to achieve a specified casting speed or by varying the tundish bath depth to modify outlet flow characteristics.
The experiments also examined the influence of the initial flow condition inside the tundish, including both stagnant and moving liquid bath conditions, on instantaneous conductivity behavior. Only minor variations in conductivity were observed between repeated trials, indicating stable and repeatable mixing characteristics.
Because the physical model was geometrically similar to the industrial tundish system, dynamic similarity conditions were satisfied. Therefore, the flow behavior and kinematic characteristics in the model corresponded closely to those in the actual steel plant tundish.
The following volume conservation relationship applies:

Where:
- (Q) = volumetric flow rate
- (A) = cross-sectional area
- (U) = flow velocity
Since the model and industrial tundish shared similar geometric and dynamic conditions, the model time scale corresponded directly to the actual casting process.

The casting strand length can therefore be expressed as:

Based on this relationship, the experimentally measured conductivity variations can be directly correlated with the actual strand length produced during continuous casting.
Relationship Between Nitrogen Pickup and Strand Length
Figure 3 illustrates the variation in conductivity measured near the tundish outlet as a function of time and corresponding strand length.

The experimental results show that conductivity remained high during approximately the first 500 seconds after startup casting. Between 500 and 800 seconds, conductivity decreased rapidly, and by approximately 1200 seconds, the conductivity approached stable steady-state conditions.
When translated into industrial casting conditions, the results indicate that nitrogen fluctuations caused by startup atmospheric exposure mainly affect the first several blooms produced from the initial tundish heat.

Extrapolation of the physical model results to steel plant operations suggests that:
- The first three blooms exhibit the most significant nitrogen fluctuations.
- Nitrogen variation decreases progressively along the strand length.
- Nitrogen content approaches stable casting conditions after approximately the fifth bloom.
These results clearly demonstrate the relationship between tundish atmospheric exposure time and the strand length affected by nitrogen absorption in steel.

Industrial Validation Using SCr420HB Steel
To further validate the physical model results, nitrogen content measurements were conducted on the first five blooms produced during continuous casting of SCr420HB steel.
Nitrogen analysis was performed using a LECO™ oxygen and nitrogen analyzer. Under identical continuous casting conditions, a total of eleven industrial trials were completed. Nitrogen contents were measured near the tail sections of the first five blooms.
The measured data revealed trends that closely matched the conductivity variations observed in the physical model experiments.
Specifically:
- Nitrogen content was highest in the first bloom.
- Nitrogen levels gradually decreased in subsequent blooms.
- Stable nitrogen conditions were achieved after several strands.
To quantitatively compare the industrial measurements with the physical model, the nitrogen content data were converted into dimensionless form.
Similarly, the conductivity measurements from the water model were normalized using dimensionless conductivity relationships.
Figure 4 compares the dimensionless nitrogen content obtained from industrial bloom measurements with the corresponding dimensionless conductivity derived from the full-scale tundish water model.

A strong correlation between the two sets of results was observed. This agreement confirms that the physical model accurately reproduces the transient mixing and nitrogen transfer phenomena occurring in the industrial continuous casting tundish process.
Influence of Long Shroud Design and Refractory Conditions
The present study clearly demonstrates that atmospheric exposure of molten steel during startup casting significantly increases tundish nitrogen pickup, particularly in the initial strand lengths.
Reducing the exposure time of molten steel jets to the tundish atmosphere is therefore essential for minimizing nitrogen absorption and improving bloom quality consistency.
One practical solution involves increasing the immersion depth or effective length of the long shroud. However, implementing such operational modifications in large-scale industrial casting operations presents several challenges.
Excessive long shroud length may:
- Increase molten steel splashing during startup teeming
- Intensify erosion in the tundish impact zone
- Accelerate wear of tundish refractory lining materials
- Increase local thermal loads and refractory stress
- Affect flow stability during startup casting
For this reason, optimization of long shroud casting conditions must consider both metallurgical performance and refractory service life.
In particular, the design of the tundish impact pad refractory, working lining, and flow control refractory system plays an important role in maintaining stable startup conditions and minimizing secondary oxidation.
The study also suggests that inert gas pre-filling of the tundish atmosphere can effectively reduce nitrogen and oxygen absorption during startup casting, thereby reducing the strand length affected by compositional fluctuations.
Conclusion
This study investigated tundish nitrogen pickup caused by atmospheric exposure during the initial stage of continuous casting using a full-scale physical water model incorporating a long shroud system.
The experimental results demonstrated that composition fluctuations resulting from molten steel exposure mainly affect the first three blooms of the first tundish heat. The conductivity variations observed in the physical model showed strong agreement with nitrogen measurements obtained from industrial casting operations.
The findings further indicate that optimizing continuous casting tundish conditions, improving long shroud casting practices, and reducing molten steel atmospheric exposure time can effectively minimize nitrogen absorption in steel and improve bloom quality consistency.
In addition, proper optimization of tundish refractory design, impact zone protection, and inert gas shielding practices can further reduce secondary oxidation and improve casting stability during startup operations.
FAQ
What causes tundish nitrogen pickup during continuous casting?
Tundish nitrogen pickup occurs when molten steel is exposed to the atmosphere before the long shroud outlet becomes submerged during startup casting.
Why is nitrogen absorption harmful in steelmaking?
Excess nitrogen can negatively affect steel cleanliness, mechanical properties, and chemical composition stability.
How does long shroud casting reduce nitrogen pickup?
A long shroud isolates molten steel from atmospheric contact during transfer from the ladle to the tundish.
What role does the tundish refractory system play?
Tundish refractory materials help stabilize flow conditions, protect the impact zone, and reduce secondary oxidation risks.


